“” background image gradient

Building the future

Your investments at work.

We are working to maintain and  improve critical infrastructure to meet state regulations and ensure our city is prepared to meet future demands.

In November 2024, City Council approved the 2025 budget and five-year rate case. The five-year rate case is a new, longer-term plan to build and maintain critical utilities infrastructure in Colorado Springs.

Through these important projects, we are building the future together.

Energy & fiber projects

This list provides projections as of April 2025 and is not all-inclusive. It highlights the largest capital projects in order of projected cost over the next five years. Projections are subject to change. 

Water & wastewater projects

This list provides projections as of October 2024 and is not all-inclusive. It highlights the largest capital projects in order of projected cost over the next five years. Projections are subject to change. 

Other current projects

In addition to the major projects listed above, we are completing additional repairs and improvements to our infrastructure.

Completed projects

An open dirt field next to six natural gas power generators at the site of the old Martin Drake Power Plant in downtown Colorado Springs.
Sustainable Energy Plan

Martin Drake Power Plant Demolition

After less than two years of careful mitigation efforts, major demolition efforts of the former Martin Drake Power Plant are complete.

Read more Read more
Aerial photo of the reconstructed section of Monument Creek and the new pedestrian ramp, access to the creek.
Wastewater project

Monument Creek Stabilization Project

We completed work in July 2024 to protect important wastewater infrastructure that lies below Monument Creek.

Read more Read more
Power poles and steel equipment at the Briargate Substation photographed under hazy/smoky skies.
Sustainable Energy Plan

Briargate Substation and Transmission Line

The Briargate Substation and Transmission Line project added infrastructure to increase transmission capacity and improve grid reliability.

Read more Read more
A large steel power pole above an electric substation on the east side of Colorado Springs.
Sustainable Energy Plan

Cottonwood-Fuller Transmission Line

The Cottonwood-Fuller transmission line conductors were replaced to increase its capacity and improve system reliability.

Read more Read more
An electrical substation with high-voltage equipment, including transformers, circuit breakers, and power lines.
Sustainable Energy Plan

Horizon Substation

The Horizon Substation is a new substation that supports transmission reliability, and the growing electrical distribution needs of our community.

Read more Read more
A worker uses a long insulated pole to interact with high-voltage electrical equipment, including large insulators and power lines
Sustainable Energy Plan

Williams Creek Substation

Williams Creek Substation was upgraded and expanded to interconnect renewable energy generation and to support a reliable, cost-effective energy system.

Read more Read more
Aerial photo of a sprawling, massive number of solar panels in a brown field with mountains in the far distance.
Sustainable Energy Plan

Pike Solar Facility

The Pike Solar Facility is now generating and delivering electricity. The 175-megawatt solar array, located on 1,310 acres, was placed into operation in December 2023.

Read more Read more
Image of a piece of equipment at an electric substation.
tag-icon Sustainable Energy Plan

Flying Horse Substation

The Flying Horse Substation received new equipment to support power from present and future renewable energy sources.

Read more Read more