The Central Bluffs Substation project combines two substations and a switch station into one modern facility. This project improves our electric grid, making it more adaptable and efficient as our needs change.
Key benefits:
- Reduces outage risks by replacing aging infrastructure with modern systems.
- Supports growing energy demand along N. Nevada Avenue and Austin Bluffs Parkway.
- Streamlines power delivery and facility maintenance.
- Allows room for future expansions and technologies.
Project timeline
✔ December 2025: Pour foundations for transformers and equipment.
✔ January 2026: Install new transformer and switchgears.
✔ January-March 2026: Finalize site grading and install grounding grid
✔ April 2026: Begin installing the perimeter wall and conduits
• May-July 2026: Install steel, switches, insulators, control building, and cables
• August-September 2026: Install busbars, breakers, jumpers and control cables
• October 2026: Install new transmission poles and complete perimeter wall
• November 2026: Replace transmission cables
• December 2026: Energize and commission substation and equipment
• January 2027: Substation in service; begin cleanup and restoration work
• February-April 2027: Complete site cleanup, restoration and vegetation/landscaping