“”

Central Bluffs Substation

We are modernizing our infrastructure for sustainability, system resiliency and reliability.


The Central Bluffs Substation project is a new electric substation built to improve electric reliability and support growing energy needs in Colorado Springs.

The new substation will combine two substations and a switch station into one modern facility for better efficiency and adaptability as our electric grid continues to evolve.

Central-Bluffs-aerial-1920-pxKey benefits:

  • Reduces outage risks by replacing aging infrastructure with modern systems.
  • Supports growing energy demand along N. Nevada Avenue and Austin Bluffs Parkway.
  • Streamlines power delivery and facility maintenance.
  • Allows room for future expansions and technologies.

Project timeline

  • December 2025: Electric distribution work and site grading.
  • January-March 2026: Install the permanent perimeter security fence/wall.
  • March-May 2026: Install vertical steel structures, grounding and conduit.
  • June-July 2026: Continue to install vertical steel structures. Install switches.
  • September-October 2026: Install overhead equipment. Begin site testing.
  • November 2026: Substation complete. Erect transmission poles.
  • December 2026: Complete transmission line work. Conduct final site testing.
  • January 2026: Project complete. Substation in service. Begin restoration.
  • March-April 2026: Final restoration and clean-up. Vegetation is planted.

Our commitment to the community

" frameborder="0" allowfullscreen>

Public input has played an important part in how this project has evolved. In response to concerns about site selection, tree removal and property impacts, we’ve prioritized:

  • Transparent communication.
  • Two-way dialogue with community members.
  • Proactive updates on construction activities and timelines.

Visit the link below to share specific feedback about this project.

Share your thoughts

Upcoming public meetings

“”

Online meeting

Date: Monday, Feb. 9, 2026
Time: 5:30 - 6:30 p.m.

“”

Online meeting

Date: Monday, April. 13, 2026
Time: 5:30 - 6:30 p.m.

“”

Online meeting

Date: Monday, June. 8, 2026
Time: 5:30 - 6:30 p.m.

“”

Online meeting

Date: Monday, Aug. 10, 2026
Time: 5:30 - 6:30 p.m.

“”

Online meeting

Date: Monday, Oct. 10, 2026
Time: 5:30 - 6:30 p.m.

Project renderings

Rendering of the Central Bluffs Substation looking west from Austin Bluffs Parkway. A tall fence surrounds electric equipment below power lines.
Rendering of the Central Bluffs Substation looking south from Goldenrod Drive. A tall fence surrounds electric equipment below power lines.
Rendering of the Central Bluffs Substation looking west from Austin Bluffs Parkway and Goldenrod Drive. A tall fence surrounds electric equipment below power lines.
Rendering of the Central Bluffs Substation looking southwest from Austin Bluffs Parkway. A tall beige fence surrounds electric equipment below power lines.

Questions & answers

Why is a new substation needed in this area?

The existing substations are aging, space-constrained and cannot be upgraded to meet current and future energy needs.

The new substation ensures safe, reliable service and supports growing energy demand in this part of the city.

Sustainable Energy Plan Projects

Our vision is coming to life. We’re working on projects across our community that improve the electric grid, reduce emissions, increase clean energy use and provide safe, affordable energy for our community.

Kelker Substation Expansion Project

Kelker Substation Expansion Project

The Kelker substation expansion project addresses our plan to improve system reliability and expand resources to meet growing energy demands.

Learn more Learn more
Jackson Fuller Energy Storage Project

Jackson Fuller Energy Storage Project

The Jackson Fuller energy storage project helps us store excess energy for use during periods of low generation or high demand.

Learn more Learn more
Horizon Substation project

Horizon Substation project

The Horizon Substation will help improve system reliability by expanding our resources to meet the growing energy needs.

Learn more Learn more
Martin Drake Power Plant

Martin Drake Power Plant

Demolition of the former Martin Drake Power Plant were completed in 2024, following nearly a century of electric generation in downtown Colorado ...

Learn more Learn more
Briargate Substation & Transmission Line

Briargate Substation & Transmission Line

The Briargate Substation and Transmission Line Project was completed in 2023, and it supports our efforts to deliver reliable energy to our community.

Learn more Learn more
Cottonwood-Fuller transmission line project

Cottonwood-Fuller transmission line project

We replaced the power line with a better conductor to increase energy flow between Cottonwood and Fuller Substations.

Learn more Learn more
Midway-Kelker Transmission Line Project

Midway-Kelker Transmission Line Project

The Midway-Kelker transmission line project supports the Sustainable Energy Plan (SEP) goal to provide safe and reliable energy systems.

Learn more Learn more
Williams Creek Substation

Williams Creek Substation

The Williams Creek substation was expanded to accommodate the new Pike Solar Array and interconnect to the transmission line from the Nixon Power ...

Learn more Learn more