The Central Bluffs Substation project combines two substations and a switch station into one modern facility. This project improves our electric grid, making it more adaptable and efficient as our needs change.
Key benefits:
- Reduces outage risks by replacing aging infrastructure with modern systems.
- Supports growing energy demand along N. Nevada Avenue and Austin Bluffs Parkway.
- Streamlines power delivery and facility maintenance.
- Allows room for future expansions and technologies.
Project timeline
✔ December 2025: Pour transformer foundations and complete site grading.
• January-March 2026: Install the permanent perimeter security fence/wall.
• March-May 2026: Install vertical steel structures, grounding and conduit.
• June-July 2026: Continue to install vertical steel structures. Install switches.
• September-October 2026: Install overhead equipment. Begin site testing.
• November 2026: Substation complete. Build transmission poles.
• December 2026: Complete transmission line work. Conduct final site testing.
• January 2027: Project complete. Substation in service. Begin restoration.
• March-April 2027: Final restoration and clean-up. Vegetation is planted.