The Central Bluffs Substation project is a new electric substation built to improve electric reliability and support growing energy needs in Colorado Springs.
The new substation will combine two substations and a switch station into one modern facility for better efficiency and adaptability as our electric grid continues to evolve.
Key benefits:
- Reduces outage risks by replacing aging infrastructure with modern systems.
- Supports growing energy demand along N. Nevada Avenue and Austin Bluffs Parkway.
- Streamlines power delivery and facility maintenance.
- Allows room for future expansions and technologies.
Project timeline
- December 2025: Electric distribution work and site grading.
- January-March 2026: Install the permanent perimeter security fence/wall.
- March-May 2026: Install vertical steel structures, grounding and conduit.
- June-July 2026: Continue to install vertical steel structures. Install switches.
- September-October 2026: Install overhead equipment. Begin site testing.
- November 2026: Substation complete. Erect transmission poles.
- December 2026: Complete transmission line work. Conduct final site testing.
- January 2026: Project complete. Substation in service. Begin restoration.
- March-April 2026: Final restoration and clean-up. Vegetation is planted.