The Central Bluffs Substation project combines two substations and a switch station into one modern facility. This project improves our electric grid, making it more adaptable and efficient as our needs change.
Key benefits:
- Reduces outage risks by replacing aging infrastructure with modern systems.
- Supports growing energy demand along N. Nevada Avenue and Austin Bluffs Parkway.
- Streamlines power delivery and facility maintenance.
- Allows room for future expansions and technologies.
Project timeline
✔ December 2025: Pour foundations for transformers and equipment.
✔ January 2026: Install new transformer and switchgears.
✔ January-March 2026: Finalize site grading and install grounding grid
✔ April 2026: Begin installing the perimeter wall and conduits
✔ May-July 2026: Install steel, switches, insulators, cable trenches and control building
✔ August-September 2026: Install breakers
• October 2026: Install busbars, control cables and three transmission poles
• November 2026: Install jumpers and connecting cables
• December 2026: Complete perimeter wall
• January-March 2027: Site cleanup, restoration and landscaping
• April 2027: Install remaining transmission poles and transmission cables
• May 2027: Energize and commission new substation