In July 2024, we began a multi-phase project to replace more than 4,400 feet of water main and add new lining to more than a mile of existing water main. This work will result in enhanced water quality and service reliability for the area.
Phases 1-3 are complete, which included the installation of a new water main. Phase 4 will begin soon to add a new lining in the existing water main to extend the life of the pipe.
Motorists should plan ahead if this is their normal route. Through traffic will still be able to pass through the work zone, but please use caution while our crews are working in this area.
Project schedule
✔ Phase 1: Moffat Circle to Wooten Road | July 2024-mid September 2024
✔ Phase 2: Wooten Road to Babcock Road | January 2025-March 2025
✔ Phase 3: Sand Creek to Space Center Drive | April 2025-May 2025
• Phase 4: Moffat Circle to Powers Boulevard | March 2026-June 2026
*This schedule is subject to change due to unforeseen circumstances, such as weather.
Work hours will typically be Monday-Friday 7 a.m.-5 p.m. Thank you for your understanding and cooperation while we work to improve our water system. If you have any questions regarding the project, please contact us at engage@csu.org or call (719) 668-7765.